Bournemouth Beach
Improvement Scheme (BIS4.3) 2008
A
section of beach between Boscombe and Southbourne was replenished
this winter by the Fareham-based
Westminster
Dredging Company, using the same Dutch dredger Oranje,
the same pipeline and the same
Ovenden
beach crew as for
BIS4.2
last year.
The project suffered bad-weather delays.
Originally projected to take just 3 days, the eight hopper loads of sandy
beach material were delivered to the beach
over a period of one week.
Beach material was dredged off
the Isle of Wight and brought by the dredger close to the beach at Groyne
30 (see map).
The dredge/sail/discharge cycle
from the IoW took approximately 11 hours.
Because the waters of Poole Bay
are so shallow, the dredger needed to pump the sand ashore through a
long pipe that lay on the sea bed, known as a 'sinkerline', and the beach
was then levelled by bulldozers.
i
For more detailed
replenishment process information and pictures see
Phase I.
Project news & updates can be
found at the project diary