Last update: 14 March 2008

Bournemouth Beach Improvement Scheme 4.3

Home

Past Projects

Studies & Research

Contacts

Useful Links

Links to Bournemouth Borough Council web site

Links to Borough of Poole web site

Links to Poole Harbour Commissioners web site

Bournemouth Beach Top-up (BIS4.3) March 2008

The Dutch dredger 'Oranje'A section of beach between Boscombe and Southbourne was replenished this winter by the Fareham-based Westminster Dredging Company and the Dutch dredger Oranje.

The project suffered bad-weather delays.  Originally projected to take just 3 days, the eight hopper loads of sandy beach material were delivered to the beach over a period of one week.

Beach material was dredged off the Isle of Wight and brought by the dredger close to the beach at Groyne 30 (see map).  The dredge/sail/discharge cycle from the IoW took approximately 11 hours.

Because the waters of Poole Bay are so shallow, the dredger  needed to pump the sand ashore through a long pipe that lay on the sea bed, known as a 'sinkerline', and the beach was then levelled by bulldozers.

For more detailed replenishment process information and pictures see BIS4.1 (opens in a new window)

Contact

Dr David Harlow, Coast Protection Manager

Bournemouth Borough Council

Town Hall Annexe

St Stephens Road

Bournemouth BH2 6EA

Tel: 01202 451389

Fax: 01202 451008

Email David Harlow

About Beach Improvement Schemes

During the 20th Century, the cliffs were protected from coastal erosion by building concrete seawalls and groynes. This allowed houses and roads to be built on the cliff tops, but it also stopped the natural supply of sand and gravel to the shore.  So beach material that is lost to natural coastal processes cannot be replaced by any other than artificial means.

Bournemouth beach loses approximately 70,000 m3 of material annually (1 million m3 every 13 years.  Since the predominant direction of longshore transport in Poole Bay is from west to east, sand gradually feeds the beaches at Southbourne and Hengistbury Head to the east, and beyond into Christchurch Bay.

The shoreline has been replenished on several occasions in recent years; these projects are referred to as 'Beach Improvement Schemes' (BIS):

Scheme

Year

Quantity of Sand (m3)

BIS1

1970

84,000

BIS2

1974/75

1,400,000

BIS3

1988/89

1,000,000

BIS4.1

2005/06

600,000

BIS4.2

2006/07

898,000*

BIS4.3

2008

70,000

*included 15,000m3 stockpiled for the Boscombe surf reef

In the past Bournemouth Council has carried out "boom & bust" replenishment schemes, where the beach is delivered with a large quantity of material (e.g. 1974/75) and left until much of it is lost before further replenishment (e.g. 1988/89).

The first stage of Beach Improvement Scheme 4 (BIS4.1, 2005/06) was part of a wider scheme that included the replenishment of beaches at Swanage and Poole using sand dredged from Poole Harbour.  The project continued at Bournemouth during the winter of 2006/2007, between Boscombe and Alum Chine, using a further supply of sand from a Licensed Dredging Area off the Isle of Wight [BIS4.2].

During the three years 2008-2010 the council pledged to make good the annual losses to keep the beach at a constant level and volume (BIS4.3, BIS4.4 and BIS4.5) Replenishment is localised and takes just a few days.  It is undertaken during winter months in order to minimise disturbance to public access & enjoyment. 

[BIS.4.1] [BIS4.2] - these projects open in new windows.   [BIS4.3 2008] [BIS4.4 2009] [BIS4.5 2010]

© 2005-10 The Poole Bay Partnership

Web development & maintenance: VIVID Websites