14th March
Oranje deposited her final load this
morning and has departed for Qatar. The sinker pipe should be
filled with air today, and towed back to Holland tomorrow (inspections &
weather permitting)
The shoreline pipe sections will start leaving
by road on Monday lunchtime, and heavy plant will leave once the beach
has been shaped.
The site should be cleared by next Thursday,
20th March (in time for the Easter holidays)
|
 |
13th March
Load 6 was
pumped ashore today at 0820 hrs between groynes 29 and 28; load 7 is
scheduled for 1800 hrs and the final load at 1600 hrs tomorrow, the
14th.
The Oranje
will then leave Bournemouth and head straight for the Qatar in the Middle East to
undertake another replenishment project there.
|
 |
12th March
The Oranje
arrived at Bournemouth with a full hopper (load 5) at 2200 hrs. |
|
|
11th March
Further
weather-related delays. The Oranje has returned to Rotterdam for
bunkering (refuelling) and is expected back tomorrow, Wednesday, at about
1500 hrs.
On her return
she will deliver three or four more loads to complete BIS4.3. |
 |
10th March
Replenishment work is delayed by the severe
gales
affecting the south west, coupled with a very high tide.
|
 |
9th March
Load 3
delivered to the beach at 0800 hrs, Load 4 at 1800hrs. |
 |
8th March
Load 1 was
delivered to the beach at 1100 hrs, Load 2 at 2200 hrs. |
7th March
The floating pipeline has arrived
from Holland and
is connected. The dredger set
sail from Rotterdam today and is due to
pump the first load of beach material tomorrow,
Saturday, at 8:00am.
50mph winds are forecast for Sunday, which
would make it dangerous for work to continue so the project is likely
to be delayed. |
 |
6th March
The beach crew have created a sand mound, and
have raised the end of the sinker pipe, all in preparation for the
arrival of the first load, now due on Saturday morning (if the weather
holds out for the 150m floating pipe and its connection).
An area from the seawall to the sea has been
fenced, preventing public access to the working area, and additional
signs will be erected advising dog walkers to put their dogs on leads to
keep them from danger.
|
5th March
The section of floating pipeline has
been delayed by bad weather. It left Holland
this morning and is due to arrive at Bournemouth tomorrow (Thursday)
afternoon. |
 |
29th February
The floating
section for the seaward end of the sinkerline left Holland and, weather
permitting,
will be arriving at Bournemouth
on Sunday 2nd March. This pipe is 150m long, and connects the sinkerline
to the dredger,
The dredger
Oranje is now due during the afternoon of Monday 3rd March.
It is expected to collect sand from the Isle of Wight en route, and
arrive at Bournemouth ready to discharge.
|
 |
27th February
Sections
of land pipeline arrived overland from Holland.
The Ovenden
beach crew are setting up site with a temporary office and sand-moving
equipment.
|
|
_web_small.jpg)
|
18th February 2008
09:00 the sinkerline arrives from Holland.
It is brought ashore at Portman Ravine and the filling air is let out,
allowing the pipe to sink to the sea bed. The seaward end is
secured, awaiting the arrival of the Oranje. |