Method of Construction
Portland
limestone was used for groyne construction, and was brought to site by road. Each rock for the
head section of groyne weighs three to six tonnes, and for the
section from the head back to the promenade one to three tonnes.
At the
beach, sand is first excavated from the area where the groyne will
be located. The area is then backfilled with a bedding layer
of stone to prevent subsidence of the groyne structure. Using this
method of construction the groyne is extended seawards with bedding
material and rock, building up to a level that will permit plant to
run on it.
As
construction progresses to full groyne length manhole rings are used
to create voids to take the piles for the walkway that allow public
access to the groyne.
Walkways
are independent structures consisting of concrete beams spanning
piles driven along the length of the groyne.
Walkway
sections and pile caps are made at the beach from reinforced precast
concrete and lifted into position.
Construction
proceeds with the head of the groyne being built to its full
height. Piles are then driven into position through the voids by a
vibrating rig (and air hammer if required). Working shoreward pile
heads and walkway sections are put into position at the same time as
rock is built up to the finished level.
The whole
operation is then able to retreat off the groyne leaving a near
completed structure; just the in situ joints and infill between the
walkways and pile heads are completed later.
Access
ramps are situated between the back of the groynes and the
promenade, made from concrete poured in-situ and tied back into the
existing stepped sea wall. First the wall sections of the
ramps are poured, then the ramp is filled with beach sand and the
slab section is cast on top.
Groyne
construction methods have changed little since groynes were first
built at Sandbanks in 1996 and again in 2001 (photos above are
from those previous projects).
What
are the large trenches/ramps for? The large
excavations at the back of the beach are for construction of ramps.
Ramps allow access, for instance, across the beach for the beach
rake and tractor. Ramp foundations are taken to below the
level of sand before beach replenishment (2006/07). The size
of the excavation is due to the working area required to provide the
long 1:20 slope that complies with Disability Discrimination Act (DDA) regulations.
Where will all the sand go?
Sand from the
excavation is placed seaward to give protection to the workforce and
the working area. Once construction work is complete the sand
will be replaced in the excavation trench. Current beach
levels will means that the majority of the ramps will then be
covered by sand; the extent of the ramps will ensure they can be
utilised if/when beach levels drop.
What other access improvements are provided by
ramps? Ramps provide visitor access from the
promenade to the beach and the groyne walkways. They also
allow easier access for the less able and those using mobility
scooter or wheelchairs, buggies and prams.
David
Robson, Senior Engineer
Coastal
& Drainage Team,
Borough
of Poole
Email:
d.robson@poole.gov.uk |