|
Project
Week 23 |
|
05 May |
Construction
of all five groynes is now complete. All that
remains is to clear the site and reinstate some areas
of the promenade.
The
photograph (top right) show the groynes looking
west toward Sandbanks with the Purbeck hills beyond.
|
|
Project
Week 22 |
|
28 April |
This week we are
finishing off the work on Groyne 4 and starting to
clear the site.
|
|
Project
Week 20 |
|
15 April |
Groynes 1,2,3 & 5 are
complete with handrails and lifebuoys fitted to the
ends of the groynes. This section of the
beach is now open.
Groyne 4 - work
continues placing rock on groyne.
|
|
Project
Week 18 |
|
02 April |
Groynes 1 &
2 completed.
Groyne 3
- infilling with small rock to plug the larger gaps
between stones.
Groyne 4 -
ramp construction completed, see photo top right.
Construction workers pleased with their efforts. Work
now starts on the walkway out to sea over the existing
outfall.
Groyne 5 -
walkways have been placed and joints between the
planks have been filled. Rock is now being placed up
to the edge of the walkway.
A riddle
bucket has been sourced to sieve the sand to remove
small discarded rocks; once that's been done the beach
can be cleaned and opened to the public. Safety
railings, signs and lifebuoys will soon be installed
at the end of groynes.
|
|
Project
Week 17 |
|
26 March |
Groynes 1 & 2 -
placing the rock to finish the groynes
Groyne 3 - ramp and
walkway sections ready for concrete to complete them
Groyne 4 - ready to
start ramp slab construction
Groyne 5 - ramp slab
construction in progress.
|
|
Week 16 |
|
|
19 March |
Groyne 1 -
ramp and walkways now complete, section of beach being
cleaned ready to re-open.
Groyne 2 -
ramp complete, placing walkway sections
Groyne 3 -
pouring concrete for ramp
Groyne 5 -
placing rock
|
|
17 March |
Groyne 1 - the last
sections of walkway have been placed ready for
concreting
Groyne 2, 3 & 4 -
work progresses on the ramps
Groyne 5 - placing
rock at the tail end of the groyne
|
|
Week 15 |
|
|
09 March |
Groyne 1 -
the ramp is almost complete; just the centre section
to finish.
Groyne 2 - work has
started on the slabs for the top of the ramp
Groyne 3 - sand has
been backfilled around the ramp and is ready for the
slab
Groyne 4 - the last
sections of ramp wall are being cast
Groyne 5 - ramp walls
are complete and the sand is being backfilled
|
|
|
Responses to
Frequently
Asked Questions have been published in response to
the many enquiries about ramp construction (additional
signage on site) |
|
Week 12 |
|
|
20 February |
Groyne 1 - ramp
wall finished and backfilled, ramp slab construction
underway.
Groyne 2 - ramp wall completed, awaiting backfill.
Groynes 3 & 5 - ramp wall construction continues.
Groyne 4 - excavation for the ramp underway.
|
|
Week 11 |
|
|
12 February |
The walkway has been
cast in place at Groyne 1 and work has started on
Groyne 2. The ramp at Groyne 1 is nearing
completion.
Rock is being place
at Groyne 2 this week, making use of the low spring
tides, and the piles for the navigation markers have
been driven for Groynes 1,2,3 and 5
|
|
11 February |
"Ancient tree
stump turns up on Poole beach" (Daily
Echo story) |
|
Week 10 |
|
|
02 February |
Despite today's snow progress continues apace on the
ramps for Groynes 1,2,3 and 5.
Work
started today on placing the walkway sections for
Groyne 1, with the first pile caps in position.
|
|
Week 8 |
|
|
22 January |
This week's neap
tides (higher sea levels and a reduced tidal
range) restricts seaward groyne construction.
Work
still continues, however, on the ramps for Groynes 1 &
2. We have also started removing the old timber
groynes to the west of Branksome Chine.
|
|
Week 7 |
|
|
15 January |
This week we took
advantage of low spring tides to work on the ends of
Groynes 1 and 2.
Work has also started
on placing concrete for the ramp at Groyne 1 and on
piling for the ramp on Groyne 2.
The
first of the precast concrete walkway sections has
also been delivered to site.
|
|
12 January |
Work
continues despite the strong south westerly winds
today:
Groyne 1 - most of
the rock has been put in place and piling for the
access ramp is half completed
Groyne 2 - rock has
been placed down to high water mark
Groyne 3 - rock
placement continues
|
|
Week 6 |
|
|
09 January |
At Branksome
Chine Wessex Water sink a new 350mm outfall pipe to the
seabed, part of a modernisation project that runs
alongside groyne construction [aerial
photos]. |
|
06 January |
Christmas break over and work resumes at Groyne 1 with
the construction of the access ramp to the landward
end of the groyne. Rock is delivered and placed at
Groyne 2, and at Groyne 3 sand is excavated in
preparation for the bedding layer.
|
|
Week 5 |
|
|
23 December |
No rock
deliveries or construction work since the 19th.
This week we've been disposing of (recycling) timbers
from the old groynes, tidying the site and opening up
as much as possible of the Branksome Chine car park.
Work resumes 05 January.
|
|
Week 4 |
|
|
19 December |
Work
starts on the bedding layer for Groyne 2. |
|
18 December |
Work has
continued this week placing the rock for Groyne 1.
It is hoped
to get most of the rock placed at this first groyne
before the Christmas break.
|
|
17 December |
Visit to site
by Councillors, press and partners |
|
15 December |
Continuing to place rock at Groyne 1
All piling for walkways now completed; the piling rig
is scheduled to leave site tomorrow.
|
|
Week 3 |
|
|
12 December |
Groyne 5 piling completed. At Groyne 1 work has
started to place rock at seaward end.
|
|
11 December |
The project team visited Portland quarry today ( pictures).
At the beach piling on groynes 2 & 3 has been completed
and work has started on
Groyne 5.
Excavation has started on the foundation for Groyne 1.
|
| |
Groyne Nos 1-5 are shown on the downloadable plan
(right) |
|
10 December |
Piling started today for the supports to the groyne
walkways; Groyne 1 piles have been completed
|
|
09 December |
First piles
for walkways arrived today |
|
08 December |
Precast concrete sections for the groyne walkways are
being manufactured at Dean & Dyball's yard in
Ringwood to be brought to site when required.
Meantime rock deliveries
continue and the old timber groynes are still being
removed.
|
|
Week 2 |
|
|
03 December |
The first
deliveries of rock arrive at the beach; work continues
to remove old timber groynes |
|
01 December |
Work continues on
making up the platform for rock deliveries, and starts
on the removal of old timber groynes.
|
|
Week 1 |
|
|
28 November |
Setting up
site |
|
27 November |
More of the
same today - site security and temporary platform
construction. |
|
26 November |
Construction
started of a temporary stone platform which will be used
for unloading rock from delivery vehicles. |
|
25 November |
Dean & Dyball
continue to fence off the working area, and start
setting out the location of the groynes.
|
|
24 November |
First day on site.
Dean & Dyball set up a working area on beach and
start to mobilise plant.
|
If
you have any comments or photographs that you would like to add to
our pages then please email the project manager,
David Robson. |