Bournemouth groyne repair works 2009/2010

Home

Past Projects

Studies & Research

Contacts

Useful Links

Links to Bournemouth Borough Council web site

Links to Borough of Poole web site

Links to Poole Harbour Commissioners web site

 

 

Links to Bournemouth Borough Council web siteBournemouth groyne repair works 2009/2010

A £1 million project to repair four of Bournemouth's groynes; two at Southbourne (groyne No's 51 & 52) in November, and two between the Piers (groyne No's 18 & 19) in December 2009. 

Work was completed in February 2010, carried out by Ringwood-based Raymond Brown Construction Ltd., on behalf of Bournemouth Borough Council.


Groyne No's 51 & 52, Southbourne

November 2009 - the damaged timber sections at the seaward end of the 35-year old groynes were replaced with Portland Stone rock armour.

The £800,000 cost of this project was 100% Grand Aid funded by Defra (the Government Department for Environment, Food and Rural Affairs) through the Environment Agency.


Groyne No's 18 & 19, Bournemouth

December 2009 - the damaged pre-cast concrete sections at the seaward end of the 40-year old groynes were replaced with Portland Stone rock armour.

The £250,000 cost of this project was 100% Grand Aid funded by Defra (the Government Department for Environment, Food and Rural Affairs) through the Environment Agency.


Site Manager's Report

Raymond Brown Construction Ltd has clinched another major contract in Dorset adding the £800,000 project at Poole Bay on behalf of Bournemouth Borough Council to the company’s expanding portfolio of work in the area. 

Work began by mobilising the main compound at Solent Beach Car Park back on the 9th of November 2009 where two 45tonne and one 65tonne excavator, a D65 dozer, 35tonne crane and two 25tonne dump truck were delivered. 

Once established and braving all weather conditions the site team set about the task of removing the two dilapidated groynes in the period running up to Christmas.  Each pile was jetted out using a high pressure jetting lance which meant the majority of the timbers were removed in large sections.  The timbers were then loaded away off site for recycling.  During the same period over 6000tonnes of locally sourced Portland rock in 5-7tonne pieces were delivered and stockpiled on the beach. 

Groyne work 2009 (click to enlarge)Following the well earned Christmas shutdown the team returned to site to find very favourable weather conditions which enabled the start of the rock placing on the 5th January 2010.  One team excavating down to the design formation level and maintaining the protective bund that surrounded the works and another team following behind placing rock. Working late into the night to capitalise on the good weather window; extremely good progress was made.  The following days weather and sea was kind and with everyone working hard for long periods, the site team were able to continue to make excellent progress.  By the evening of Monday 11th, only one week after the first rock was placed, one of the two groynes had been completed setting the record for the fastest groyne constructed in Poole Bay according to Bournemouth Borough Council.

R.Hayman – Site Manager

January 2010.


Frequently Asked Questions

Why are groynes needed?

The whole of Poole Bay from Sandbanks to Hengistbury Head is an eroding coastline.  In order to safeguard cliff-top property and infrastructure, a long-term programme of engineering works must be implemented.

The beach replenishment projects undertaken in 2006 and 2007 delivered more than 1.5 million cubic metres of beach material to Bournemouth's coastline.  The resulting wide beaches have been a success in terms of their function as a coast protection structure and for the enjoyment they provide to Bournemouth's residents and visitors.  Beach control structures are now required to ensure they remain that way for as long as possible.

Groynes have been used extensively in the UK and abroad to tackle coastal erosion.  They work by reducing the wind and wave-driven movement of beach material along the coast, and by trapping and holding sand within the groyne bays.

Why rock groynes?

  • Rock groynes are relatively simple to construct, are extremely durable and, due to their semi-permeable nature, have the ability to dissipate the erosive power of wave energy. 

  • The main construction material (Portland Stone) is locally sourced.

  • Over time rock groynes become colonised by a range of sealife that would otherwise be missing from our flat sandy beaches

What plans for further coast protection?

The beaches will be monitored and the Council will continue to work with Defra and the Environment Agency on any future beach replenishment and any groyne repair/replacement projects that may be necessary.  Such work will be carried out as part of the local Shoreline Management Plan, which was reviewed 2009/2010.

Rock Groyne Ecology

Seaweed on rock groynes at SandbanksSince the construction of rock groynes elsewhere in Poole Bay various ecological benefits have become apparent as they became colonised firstly by lower plants such as algae and lichens.

Barnacles and seaweeds established themselves after a few years, followed by the limpets, anemones, crabs and other life forms that are able to adapt to the ever-changing tidal conditions of rocky shorelines. 

In this way, rock groynes add to the diversity of beach life, and provide inspiration for a new generation of wildlife enthusiasts.

 

This product includes mapping data licences from Ordnance Survey © Crown Copyright and/or database right License Number 10024248

© 2005-2010 The Poole Bay Partnership

Web development & maintenance: Sarah Austin