 Five new rock groynes for
Poole
Since
Poole’s beach is now wide enough to function as a coast protection
structure, controls are required to ensure it remains that way for
as long as possible.
The
Council’s Coastal & Drainage team recently received
planning permission for the construction of five new rock groynes at
Branksome Chine and Branksome Dene Chine, each measuring between
45m-75m in length.
The contract
was awarded to
Dean & Dyball and construction work commenced 24th November 2008
with completion scheduled for
1st May
2009.
This allows for a two week shut-down of
the site over Christmas (22nd December 2008 to 4th January 2009) and
one week over Easter (9th to 17th April 2009).
Some
20,000 tonnes of rock will be delivered to the beach by low-loaders
transporting up to 500 tonnes daily via the car park at Branksome
Chine.
Access to the promenade will be maintained
while construction takes place. However, to ensure public safety,
the stretch of beach from Branksome Chine to Branksome Dene Chine
will be closed while the heavy plant and machinery is on site.
Every attempt will be made to manage and limit disruption to public enjoyment of the beach.
The
cost of this project is covered by government funding from Defra and is
expected to total £1.9 million.
Once the groynes are constructed we will
create new Safe Swimming Zones between them using yellow markers.
These RNLI approved zones have been successful at Sandbanks.
Project Context
The
choice of rock groynes for this latest project followed more than
three years of detailed investigations and analysis by
HR Wallingford.
Engineers from Italy,
Holland and New Zealand were involved in the first stage of the
study which considered
more than 20 options for beach control structures. A final report
recommended four options for detailed consideration - three groyne
options and one submerged reef option. An economic appraisal
concluded that rock groynes were the preferred option.
This project
at Poole is a move away from the traditional coastal protection
scheme in that a post project appraisal and programme of beach
monitoring is being funded by Defra as part of the overall scheme,
and will compare outcomes with computer modelling by HR Wallingford.
The results will inform Environment Agency research, and help the
refinement of beach plan shape models in the future.
|